scorecardresearch
Assam: Double line between Bamunigaon–Chhaygaon stations gets commissioned

Assam: Double line between Bamunigaon–Chhaygaon stations gets commissioned

The Commissioner of Railway Safety (CRS)/NF circle Brijesh Kumar Mishra completed the statutory inspection of the newly laid double line between Bamunigaon and Chhaygaon stations on February 28, 2024.

advertisement
Double line between Bamunigaon–Chhaygaon stations gets commissioned Double line between Bamunigaon–Chhaygaon stations gets commissioned

The Commissioner of Railway Safety (CRS)/NF circle Brijesh Kumar Mishra completed the statutory inspection of the newly laid double line between Bamunigaon and Chhaygaon stations on February 28, 2024. 

Consequent upon the inspection, he has permitted the operations of trains through the newly laid portion at a maximum speed of 90 kmph.  

This newly laid second line will be helpful for carrying more freights and passenger traffic through this route.

The Bamunigaon- Chhaygaon section is a part of the New Bongaigaon – Kamakhya via Goalpara 176 km double line project. Works are being done section-wise and commissioned part by part. The stretch between Bamunigaon to Chhaygaon is of 8.782 km. 

Speed trial on the section along with through inspection of all bridges, RUB and Signaling systems was done by the Commissioner of Railway Safety (CRS)/NF circle. Modern technologies were implemented like robust track structure of all wide base Pre-stressed Concrete (PSC) sleepers & Thick Web Switches which are newly designed sturdier switches on pre-stressed concrete sleepers and can handle higher speeds of trains for this double line territory.

Also Read: All Assam Students' Union to intensifies anti-CAA protests, announces bike rally on March 4

It is to be mentioned here that with laying of double line infrastructure, movement of trains, (passengers and freights), can be done in both directions without stop-over for crossings at stations which will increase the punctuality of trains. More trains can be operated with enhanced speed thus enabling better connectivity with minimal time frame.

Earlier, on 17th October, 2023, 25.459 km section between Dhupdhara- Bamunigaon, on 3rd May, 2023, 11.35 km section between Mirza–Azara & on 24th November, 2022, 29.71 km section between Dudhnai to Dhupdhara was commissioned. On completion of this entire section of New Bongaigaon – Kamakhya via Goalpara, the northeast connectivity will get a significant boost towards transportation of both man and materials with rest of the nation. Far-flung areas of Meghalaya will also be highly benefited with the completion of this double line project between New Bongaigaon and Kamakhya via Goalpara.

Edited By: Atiqul Habib
Published On: Feb 29, 2024